Wertach Hospital Schwabmünchen
Heat and cooling energy
The company Gassner has realized the renovation of the heating and cooling system at the Wertachklinik in Schwabmünchen. For this project, a block heat and power plant with storage tank as well as a gas condensing boiler were installed. The existing hydraulics were converted to suit. During the renovation phase, the hospital was supplied with heat for the heating of drinking water via an existing gas boiler. This was temporarily connected to the network and removed after the new system was completed.
Two water-cooled compression refrigerators were also installed. A glycol recooler is installed on the roof of the energy center for recooling.
The current renovations at both Wertach hospitals, which have already been finished at the Bobingen hospital, are directed at improving patient comfort and adapting the spatial conditions to modern medical equipment.
Technical data:
- Buderus Logamatic 5311 control unit
- Buderus condensing boiler Logano plus SB3745
- Buderus cogeneration module Loganova plus EN140
- Buderus buffer storage tank 18,000 liters
- Reflex basic vessel VG 3000
- Reflex basic vessel Variomat VG 3000
- Sirch buffer tank cold 3000 liters
- Trane refrigerating machine CGWN206
- Weishaupt gas burner G20
- Recooling units WAVA500SPL
- Stratos Maxo pumps
Image source aerial view: Karl Rosengart
Image source entrance area: Matthias Baumgartner